Excavation & Earthwork

How to Calculate Excavation Volume

Excavation volume step by step: rectangular digs, trenches with sloped sides, average-depth method for uneven ground, soil swell, and truckload planning.

Quick answer: Bank volume (yd³) = length × width × depth in feet ÷ 27. For sloped-side trenches use the average of top and bottom width. Then multiply by a swell factor (1.12–1.5 by soil type) to get the loose volume you must haul.

Excavation estimates go wrong in two places: the geometry (sloped sides and variable depth are not box shapes) and the physics (soil expands when dug). Master both and your skip, truck, and disposal budgets land on target.

Shape 1: Rectangular pad or basement

Bank volume (yd³) = L × W × D ÷ 27  (all in feet)

A 24 × 30 ft foundation dug 4 ft deep: 24 × 30 × 4 = 2,880 ft³ = 106.7 yd³ in place. If the sides will be laid back for safety (they should be, beyond 4–5 ft depth), add the sloped wedges - see shape 3.

Shape 2: Vertical-wall trench

Volume = Width × Depth × Length ÷ 27

A utility trench 2 ft wide, 3 ft deep, 60 ft long: 2 × 3 × 60 = 360 ft³ = 13.3 yd³. Vertical walls are only safe (and legal, if anyone enters) up to limited depths - OSHA requires protection at 5 ft.

Shape 3: Sloped sides - the trapezoid method

Volume = (Top width + Bottom width) ÷ 2 × Depth × Length ÷ 27

Sloping trench walls for safety adds real volume. A drain trench with 2 ft bottom, sides laid back 1:1 (45°), 3 ft deep: top width = 2 + 2×3 = 8 ft. Volume = (8+2)/2 × 3 × 60 ÷ 27 = 33.3 yd³ - 2.5× the vertical-wall estimate. Sloping is a major volume driver; never quote a deep trench from bottom width alone.

Shape 4: Variable depth - the grid method

Real ground isn't level. Stake the area, measure the cut depth at each corner and the center (more points for bigger areas), and average:

PointCut depth
NW corner1.2 ft
NE corner1.8 ft
SW corner2.4 ft
SE corner3.0 ft
Center2.1 ft
Average2.1 ft

A 20 × 40 ft area × 2.1 ft average = 1,680 ft³ = 62 yd³ bank. The more irregular the ground, the more measurement points you need - professionals model this with survey data, but a 9-point grid gets a homeowner remarkably close.

Then apply swell - always

Soil expands 12–50% when excavated. The hole's volume is not the pile's volume:

SoilSwell62 yd³ bank becomes
Sand/gravel12%69 yd³ loose
Mixed earth25%78 yd³ loose
Clay30%81 yd³ loose

Full explanation in Soil Swell Explained; truck planning in How Many Dump-Truck Loads?

All three shapes plus swell factors are built into the excavation calculator.

Open the Excavation Calculator

Common mistakes

Quoting disposal from bank volume. Skips and trucks fill with loose soil. Budget disposal at bank × swell or you'll book ~25% too few loads.

Ignoring the slope wedges. Any excavation deeper than ~4 ft that a person will enter needs laid-back sides or shoring; laid-back sides multiply volume, as shown above.

Forgetting working room. Foundation digs need 2–3 ft of clearance beyond the wall line for formwork and waterproofing - that perimeter band is often 30%+ of the total dig.

Topsoil in the same pile. Strip and stockpile topsoil separately; it's valuable for finish grading and shouldn't pay disposal fees.

Safety: Call 811 before digging - it's free and legally required. Never enter an unprotected trench 5 ft or deeper; a collapsing trench wall exerts thousands of pounds and gives no warning.

When to call a professional

Excavations deeper than 5 ft, near foundations or property lines, below the water table, or in ground that has been filled or shows instability need an experienced contractor - and for structural support or steep temporary slopes, a geotechnical engineer. Machine work near buried utilities is a job for pros with locating experience even after 811 marks.

Frequently Asked Questions

How do I calculate excavation volume in cubic yards?

Length x width x depth in feet, divided by 27. A 20 x 30 ft pad dug 2 ft deep is 20 x 30 x 2 / 27 = 44.4 cubic yards in place - about 55 cubic yards loose after swell.

How do I calculate a trench with sloped sides?

Average the top and bottom widths, then treat it as a rectangle: (top + bottom) / 2 x depth x length. A trench 4 ft wide at top, 2 ft at bottom, 3 ft deep, 50 ft long = 3 x 3 x 50 = 450 ft3 = 16.7 yd3.

What if the excavation depth varies?

Use the average-depth method: measure depth at a grid of points (corners plus center minimum), average them, and multiply by the plan area. For long cuts, average depths at regular stations along the run.

How much does excavation cost?

Machine excavation typically runs $50-200 per hour or $5-15 per cubic yard depending on access, soil, and disposal distance. Hauling and disposal often cost as much as the digging - estimate loose volume for that part.

Should I calculate bank volume or loose volume?

Both, for different purposes: bank (in-place) volume measures the dig and is what excavation contractors usually price; loose volume (bank x 1.12-1.5 swell factor) sizes trucks, bins, and disposal fees.