Frequently Asked Questions

How much does excavation cost in 2026?

Contractor excavation for residential projects typically runs $50 to $200 per cubic yard depending on soil, access, and depth. Hauling spoil off-site adds $8 to $25 per cubic yard, and lot grading runs $0.08 to $2.00 per square foot.

What is soil swell and why does it matter?

Dug soil occupies 12-50% more volume than it did in the ground: sand swells about 12%, mixed earth 25%, clay 30%, blasted rock up to 50%. Haul-away and disposal must be estimated from the swelled loose volume, not the hole size.

How many yards of dirt fit in a dump truck?

Single-axle trucks haul 5-6 cubic yards and tandem-axle trucks 10-14, but weight often governs first: moist earth at 2,200-2,700 lb per cubic yard can max out legal payload below the bed's volume.

Do I need to call 811 before digging?

Yes. U.S. federal law requires contacting 811 a few business days before any excavation so buried utilities can be marked. The service is free, and skipping it risks injury, outages, and liability.